Galvanised service platforms and tower internals in S355J2
1,180 t across 386 welded assemblies: platform frames, access ladders, tower door frames and cable trays, hot-dip galvanised to EN ISO 1461 and trial-assembled before both shipments.
Figures from the project quality dossier. Certificate holders are named per the certificate register; Leading Top Union coordinated engineering, inspection follow-up and export documentation.
What made it hard
EXC3 is not a label on the drawing, it is a documentation regime: each assembly needs its own welded-joint register, NDT record and dimensional report, and the purchaser's inspector reads them against the ITP before galvanising, not after. Galvanising then adds a second distortion risk, because a 6 m ladder frame that is straight in the shop can bow in the zinc bath.
How we controlled it
Welding was split by thickness band so each band ran on a WPS that had actually been qualified for it, with consumables and preheat recorded per joint. Trial assembly happened in the shop on shims before galvanising, so the site bolted connections were proved against the real mating parts rather than against a drawing. NDT sampling was agreed with the purchaser up front: 100% visual, 20% UT on butt welds, with any repair re-tested in full.
Result
Both shipments left with complete EXC3 documentation packs, the trial assembly closed without site reaming, and the galvanising thickness results sat above the 85 um minimum through the sample. Delivery ran 24 weeks from drawing release to the second container, with the split into two shipments keeping the customer's erection sequence intact.
What we would check first on a similar job
Start from the welded-joint register, not the drawing: if the joint types are not classified, the NDT sample cannot be agreed and the galvaniser will be asked to cover welds nobody has inspected. Then fix the trial-assembly scope, the galvanising drainage holes, and who signs the dimensional report. Those four items decide whether EXC3 documentation closes on schedule.
Same process on your drawings
Send the drawing and specification set; we reply with the fabrication route, the inspection plan and the certificate requirement per item.