Case study · heavy steel

1,180 t EN 1090-2 EXC3 wind structures

Galvanised S355J2 service platforms and tower internals for offshore wind: what made the job hard, how weld distortion and dimensional control were handled, and what the inspection data showed at the end.

UHV-capable process chambers in 316L and aluminium — welded, electropolished, helium tested to 1 × 10⁻⁹ mbar·l/s and CMM verified to ±0.02 mm.

Northern European wind balance-of-plant contractor (anonymised) · 2025
← All case studies

Galvanised service platforms and tower internals in S355J2

1,180 t across 386 welded assemblies: platform frames, access ladders, tower door frames and cable trays, hot-dip galvanised to EN ISO 1461 and trial-assembled before both shipments.

Tonnage
1,180 t
Standards
EN 1090-2 EXC3; EN ISO 3834-2; EN ISO 1461; EN 10204 3.1
Inspection
100% VT to EN ISO 5817 level B; 20% UT to ISO 17640 on butt welds; trial assembly fit-up check; galvanising thickness at or above 85 um
Delivery
24 weeks

Figures from the project quality dossier. Certificate holders are named per the certificate register; Leading Top Union coordinated engineering, inspection follow-up and export documentation.

What made it hard

EXC3 is not a label on the drawing, it is a documentation regime: each assembly needs its own welded-joint register, NDT record and dimensional report, and the purchaser's inspector reads them against the ITP before galvanising, not after. Galvanising then adds a second distortion risk, because a 6 m ladder frame that is straight in the shop can bow in the zinc bath.

How we controlled it

Welding was split by thickness band so each band ran on a WPS that had actually been qualified for it, with consumables and preheat recorded per joint. Trial assembly happened in the shop on shims before galvanising, so the site bolted connections were proved against the real mating parts rather than against a drawing. NDT sampling was agreed with the purchaser up front: 100% visual, 20% UT on butt welds, with any repair re-tested in full.

Result

Both shipments left with complete EXC3 documentation packs, the trial assembly closed without site reaming, and the galvanising thickness results sat above the 85 um minimum through the sample. Delivery ran 24 weeks from drawing release to the second container, with the split into two shipments keeping the customer's erection sequence intact.

What we would check first on a similar job

Start from the welded-joint register, not the drawing: if the joint types are not classified, the NDT sample cannot be agreed and the galvaniser will be asked to cover welds nobody has inspected. Then fix the trial-assembly scope, the galvanising drainage holes, and who signs the dimensional report. Those four items decide whether EXC3 documentation closes on schedule.